Reporting/Approval of Cost Increases (Reprogramming)

Download QMS Version

flow chart
 

Purpose:  This process describes how the total Army team (GD, COS, MSC, HQUSACE, Installation, IMCOM, OACSIM) handles reprogramming actions (Below Threshold and Above Threshold). The COS is responsible to provide timely CWE information to the GD PM so the CWE spreadsheet and other description of the project can be developed.

References: 

  • FY08 MCA/UMMCA/AFH/BRAC Execution Guidance Memo, 10 Apr 08
  • AR 420-1, Army Facilities Management, 12 Feb 08
  • FY08 Consolidated Appropriations Act, P.L. 110-161, 26 Dec 07 (BRAC)
  • FRAGO 16 (FY 08 Mil Pgms Construction CWE/Funds Request Calculation Spreadsheet) to OPORD 2007-20
  • MCA, UMMCA, AFHC Reprogramming Requests & Notification of Scope Reduction Actions Guidance, 6 Jun 06 (currently being revised)

Process:

  1. In situations where the project CWE exceeds the PA, the Cost Issue Resolution process will be used to resolve the issue. The GD PM is responsible to fully document the CWE/PA issue in P2 Issues comment field.

  2. AR 420-1 describes the processes and requirements for Below Threshold Reprogramming (BTR) and Above Threshold Reprogramming (ATR). GD PMs will follow the guidance in the FY08 Execution memo, AR 420-1 and Reprogramming Requests and Notification of Scope Reduction memo dated 6 Jun 06 to process BTR and ATR reprogramming action

    The COS is responsible to provide CWE information for their portion of the project to the GD. The current approval thresholds are:

      New Awards
  MCA BRAC
     Approval Authority
Limits of Approval Authority (Appropriations) Limits of Approval Authority (Approp.)
     USACE, DMP
At or below PA At or below PA
     OACSIM
Up to 115% of PA or $1.5M above PA (whichever is less)
     DASA (I&H) Up to 125% of PA or $2M (whichever is less) Increase or reduction up to 20% or $2M (whichever is less)
     Congress Above 125% of PA or $2M above PA Increase or reduction exceeding 20% or $2M (whichever is less)

      Mandatory Modifications to Existing Contracts:
  MCA BRAC
     Approval Authority
Limits of Approval Authority (Appropriations) Limits of Approval Authority (Approp.)
     USACE, DMP
Up to 115% of PA or $1.5M above PA (whichever is less) Up to approved and funded CWE
     DASA (I&H) Up to 125% of PA or $2M above PA (whichever is less) Increase or reduction up to 20% or $2M (whichever is less)
     Congress Above 125% of PA or $2M above PA Increase or reduction exceeding 20% or $2M (whichever is less)

      Discretionary Modifications to Existing Contracts:
  MCA BRAC
     Approval Authority
Limits of Approval Authority (Appropriations) Limits of Approval Authority (Approp.)
     USACE, DMP
None None
     OACSIM Up to 115% of PA or $1.5M above PA (whichever is less) Increase or reductin up to 20% or $2M (whichever is less)
     DASA (I&H)

Up to 125% of PA or $2M above PA (whichever is less)

Must have OACSIM approval of discretionary change

 
     Congress

Above 125% of PA or $2M above PA

Must have OACSIM approval of discretionary change

Increase or reduction exceeding 20% or $2M (whichever is less)
 
  1. The RIT is responsible for ensuring the BTR and ATR packages are prepared and staffed through HQUSACE and submitted to OACSIM in order to obtain approvals within the needed timeframes.

Process Owner: HQUSACE PID (Maryann Delaney/202-761-5775)